1. Introduction and overview of the project
contract numberMP-89-1-000-0056
Start date01/20/90
Project Duration16 months

  1. Project Purpose
    Sheikh Baha’i building located in West Emdad St., North Sheikh Bahai Avenue  was considered to be used as with the future developments of the MAPSA company and was completed after 16 months.

3 .Advantage
A significant reduction in the costs by recruiting administrative techniques performed by experienced team

  1. Location and General Specifications
No. 5, West Emdad St., North Sheikh Bahai AvenueBuilding location
8/644 sq.m.Land area
1/3362 sq.m.Building area
6/1777 sq.m.Residential useful area
5/1584 sq.m.joints Area
7 floor (2 floors basement, pilot and four residential floors)Number of floors
Concrete structure – middle framedStructural system
Cement BlocksRoof Systems
Full implementation of the provisions of article 19 of the National Building RegulationsOther Description

5 .Floor area

  Residential  Storage and utilitiesParkingStaircaseSum
 FloorsNo. of Units Area                       No. of Units Area No. of UnitsAreaNo.of Units AreaNo.ofUnitsArea
Underground 1 474/80 23/50 498/30
Underground28 474/80 23/50 498/30
 Ground 9 386/80 111/50498/30
 1st floor 2 444/20 23/50 467/70
 2nd floor
 3rd floor
 4th floor
 Sum8 1776/808 474/8023 861/60252/50

6 .Equipment and Materials

 Buildings
 Rustic style Grade 1Floor
Nescafe colored- Travertine Tier 1Stone and walls for stairs
 MDF with PVC coated and Turkish anti-theft doorDoors and frames
 Rustic style stone Grade 1Pilot
 8-person elevator-Alberto Sassi Italy motorElevator
View
 Wood and glass and composite sheetexterior
 Double-glazed windows of aluminum Turkish thermal breakthe Windows
 Wood used in the facade and other parts, Tremwood Lunawood brand FinlandWood used in the facade
Mechanical Installations
Water
 Sewage pipe New pipe fittingsWastewater
 Council duct fan coil heating and cooling system from LGHeating and cooling
Wiring and Contacts
 Potential 25 telephone lines for every unitPhone
 polyamide tubesTubes
 Afsharnejad Khorasan Cableswire and cable
 CAT6 network –Legrand, FranceWireless  Network
 All rooms and halls are equipped with built-in computer network systems and earthing and uninterruptible power supply UPSOther

7 .Functions for Floors

1, -2 Basement:
Sauna, locker rooms, gym, buffet, kitchen, BATHROOMs, warehouse
2, -1 Basements:
Service spaces (parking, Praying Room, BATHROOMs and dining room)
3 Ground floors:
Conference hall, meeting rooms, Janitor’s room
4 Floors:
Two separate units with partitioning potential with administrative function

  1. stages of construction
    1 excavation:
    Due to the low level of the floor adjacent buildings and excavation height, height of 2 m diameter piles of 8.0 m below the walls of the excavation was done (excavation height: about 5 m).
    4 m and 6 m height guard structures based on plans of action was used in excavation stage

2: Foundation and Structure:
Structural calculations in accordance with the valid regulations and the especially the 2800 National Building Regulations were done.
Bilateral strip foundation 150 and 170 cm wide and 95 cm height have been implemented. Rebar and concrete have been tested by the laboratory

3: Structure:
Load Carrier system is resisting seismic lateral force in the average concrete moment frame in this buildings. Application of readily-mixed concrete, concrete and rebar tests were taken in laboratory and results were controlled.


4: Stairs
To provide space light through the skylights in the center of the building, slot designed adjacent to the main staircase was used.

5 .Equipment and Materials:

Did you find apk for android? You can find new Free Android Games and apps.